March
Now that we have better weather there is visible progress every day.
Please find this months detailed newsletter here
Now that we have better weather there is visible progress every day.
Please find this months detailed newsletter here
Read the newsletter HERE
The steel frame was completed prior to the scheduled Christmas construction shutdown with the roof a wall cladding in progress. Due to inclement weather the project has slipped a week, but the contractor believes this will not impact the overall schedule.
Read the full January Newsletter HERE
There is at last something to see. The steel frame is going up and hoped to be completed before the team break for Christmas
for a more detailed update the December newsletter can be read here
Building of the Hall is gathering speed. There will be a visible building very soon.
The latest newsletter can be found here
September 2025
Over the past four weeks, significant progress has been made toward enabling physical activity on site. The total estimated project cost remains at £976,460, with a slight reduction in contingency. Construction is scheduled to commence in late September early October and is expected to be completed within 36 weeks.
Read the newsletter here
August 2025
Everything is coming together, lots happening behind the scenes now. Read the Newsletter HERE
Good news for this month – we have had our Public Works Loan approved. 😀
read the Newsletter HERE
There has been little progress this month due to several key milestones being delayed for various reasons beyond our control. Even with these delays the goal remains to have the new hall open in April 2026. You can read the monthly newsletter No. 4 HERE